Visibility of Assigned Calendar Column

Post by Ken »

How can I display a column that shows the specific calendar assigned to each activity?
Ken the PM
Intaver Support
Posts: 1057
Joined: Wed Nov 09, 2005 9:55 am

Re: Visibility of Assigned Calendar Column

Post by Intaver Support »

To see the calendars assigned to individual tasks, you need to add the Task Calendar column to your view.