Activities Using Incorrect or "Unknown" Calendars

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Ken
Posts: 80
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Activities Using Incorrect or "Unknown" Calendars

Post by Ken »

Why does it appear that RiskyProject is using an unknown default calendar for activities even though the correct calendar seems to be assigned?
Ken the PM
Intaver Support
Posts: 1057
Joined: Wed Nov 09, 2005 9:55 am

Re: Activities Using Incorrect or "Unknown" Calendars

Post by Intaver Support »

Analysis of the imported data shows that calendars are generally picked up correctly. However, if the Default Start Time in the global options differs from the source file, it can simulate the appearance of an incorrect calendar. Additionally, users should verify the settings in File > Options > Calendar to ensure the software’s global rules align with the specific requirements of the project.
Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com