Discrepancy in Schedule Dates and Durations in XER
Moderator: Intaver Support
Discrepancy in Schedule Dates and Durations in XER
Why are the finish dates and task durations in days not matching between Primavera P6 and RiskyProject after importing an XER file?
Ken the PM
-
Intaver Support
- Posts: 1057
- Joined: Wed Nov 09, 2005 9:55 am
Re: Discrepancy in Schedule Dates and Durations in XER
This is typically caused by a difference in Project Start Time settings rather than a failure to import calendars. Even a small difference (e.g., 6:00 AM vs. 8:00 AM) creates a shift across the entire schedule. To fix this, ensure the Project Start time in RiskyProject matches the exact start time defined in the XER file.
Intaver Support Team
Intaver Institute Inc.