Karmal S.
Joined: 17 May 2007 Posts: 2 Location: Canada
|
Posted: Tue Dec 04, 2007 5:47 pm Post subject: Risk correlations |
|
|
Can I enter correlations between different risks? _________________ Karmal S.
Project Manager
New Product Development |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Tue Dec 04, 2007 5:50 pm Post subject: |
|
|
For both local and global risks you may enter correlations between different risk. In fact correlations in RiskyProject is implemented by setting up the same seed for different risks. RiskyProject does not ask you to enter a correlation coefficient. All risks have strong positive correlations. _________________ Intaver Support Team |
|
| Back to top |
|
 |
David
Joined: 15 Jan 2008 Posts: 3 Location: UK
|
Posted: Tue Jan 15, 2008 5:41 pm Post subject: |
|
|
I did not understand how can I enter information about risk correlations in RiskyProject? _________________ PMP, M.Sc. |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Tue Jan 15, 2008 5:55 pm Post subject: |
|
|
Risk Correlations can be entered in Risk Information Dialog for local and global risks. You may access this dialog by double clicking on RiskID within a list of local risks or in global risk view. You need to select the risk, current risk will be corrected with. _________________ Intaver Support Team |
|
| Back to top |
|
 |
Sornix
Joined: 14 Dec 2007 Posts: 4 Location: USA
|
Posted: Fri Aug 22, 2008 2:52 pm Post subject: |
|
|
RiskyProject offers strong positive correlation between risks (coefficient 1). Is it possible to define correlation coefficient not equal 1, for example 0.5? _________________ Manager Business Development |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Fri Aug 22, 2008 2:54 pm Post subject: |
|
|
We did not implement different correlation coefficient simply because our client did not ask about it. However we are planning to implement it next year in RiskyProject 4. _________________ Intaver Support Team |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Sat Oct 18, 2008 10:06 pm Post subject: |
|
|
Strong correlation between different risks in most real life project is quite sufficient. For example you have risk "Change requirements". This risk would be strong correlated with risk "Budgetary Problems". Please remember, that correlation does not mean causation. "Change requirements" would not cause "Budgetary Problems" and vice versa. Both risks most likely occur together because they would be triggered by the same factor. _________________ Intaver Support Team |
|
| Back to top |
|
 |
remi7
Joined: 21 May 2009 Posts: 1
|
Posted: Fri Jul 24, 2009 7:47 am Post subject: |
|
|
| I have the same risk assigned the two different tasks. Are two risk assignments correlated with each each other? |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Fri Jul 24, 2009 7:53 am Post subject: |
|
|
No. Each risk assignment is completely independent. For example risk "Budgetary Problems" can be assigned to task Development and task Implementation. But if "Budgetary problems" occur during development it does no mean that it will occur during Implementation.
On order to correlate risk assigned to different tasks, you should use Risk Correlation tab in Risk Information Dialog (Global and Local Risk Assignment). _________________ Intaver Support Team |
|
| Back to top |
|
 |
Interstate
Joined: 06 Mar 2006 Posts: 4
|
Posted: Wed May 19, 2010 8:28 pm Post subject: Risk relationships parent child |
|
|
| Is it possible to define risk relationships, parent/child etc in RiskyProject. A Risk that can cause additional risks where the first risk is the parent and the second is the child? |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Wed May 19, 2010 8:31 pm Post subject: Defining relationships between risks |
|
|
In the upcoming version 4, you will be able to clearly identify trigger risks (parent) and residual (child) relationships for a particular risk. You define this relationship in the Properties tab of the Risk Information dialog box. _________________ Intaver Support Team |
|
| Back to top |
|
 |
RiskUser
Joined: 11 Jun 2010 Posts: 1
|
Posted: Tue Jul 06, 2010 11:02 am Post subject: Risk relationships |
|
|
| By defining these relationships, does this define an risk event chain? |
|
| Back to top |
|
 |
Intaver Support
Joined: 09 Nov 2005 Posts: 267
|
Posted: Mon Jul 19, 2010 10:01 am Post subject: Risk relationships |
|
|
The new risk form will allow you to define trigger and residual risks for each identified risk. This is for reporting purposes and as seen in the current requirements will not define an actual correlation between the risks for purposes of Monte Carlo simulations.
The ability to define correlations using the risk triggers and residual risks as part of Monto Carlo simulations is currently in our development plans.
Intaver Support _________________ Intaver Support Team |
|