Earned Value Management
RiskyProject performs earned value analysis based on baseline project schedule and project schedule with risks and uncertainties (results of analysis). RiskyProject allows you to specify or calculate actual cost for each task. Actual cost, budgeted cost, and cost as a result of analysis (with risks and uncertainties) are displayed using interactive cash flow diagrams. You can determine difference between actual and budgeted cost on the each stage of the project.
You can view a project cash flow monthly. The cash flow analysis view shows monthly, bi-monthly, quarterly, and yearly cost and income allocation. You can also apply Net Present Value (NPV) discount rates and internal rate of return (IRR). The Cash flow view includes cost and income data in both table and chart format for the current schedule, results of analysis, and actuals.