Adding a deadline to a task
1. Select the task to which you want to add a deadline.
2. Open the Task Information
dialog box. Click the Deadline tab.
3. Enter a maximum duration in the Maximum
task duration boxes.
4. Select the time unit from the drop-down list.
5. Click on the Task Deadline box.
A calendar opens.
6. Select a date from the calendar.
7. Select an action that will occur if the task reaches the deadline
from the Action for Probabilistic Calculation
option box.
8. Click OK.
See also
Task Deadlines
|